John Cooper, Nigel Graham, Pete Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. A cold and windy day, storm Dave on its way. John and Adrian to the bottom to decide the plan of attack. Capping commenced. Meanwhile the rest were sorting out the rock heap on the surface, large rocks for walling and small for track maintenance. John was then replaced by Kate. A total of 20 loads of rock and 3 of mud were hauled out today. May need something a bit stronger next time. 3 hours. John.
Frog Pot
Saturday, April 4, 2026
Saturday, March 21, 2026
Saturday 21st March 2026
John Cooper, Nigel Graham, Pete Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. A warm sunny day with little wind. Adrian and John to the bottom intially whilst Kate organised disposal of the existing spoil on the surface. Adrian was capping and using caps and p/fs to break up rock whilst John was using the sledge hammer. Once adequate spoil was ready John was replaced by Kate at the dig face. 25 loads of spoil were then hauled to the surface. 3 hours. John.
|
|
| View down at end of session. Photo AV. |
| Closer view of hole in floor. Photo AV. |
| Another view. Photo AV. |
| Under. Photo AV. |
| Closer. Photo AV. |
Saturday, March 14, 2026
Saturday 14th March 2026
John Cooper, Nigel Graham, Pete Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. Kate to the bottom fastening the bottom ladder, only 1 rung overlap now. Loads of rock and mud were then hauled out. After Kate came out Adrian and John went down. Draught was tested – going in today. Then more rock was broken up and John went out to be replaced by Jude. More rock and mud hauled out giving a total for the day of 47 loads of rock and 7 loads of mud. 3 hours. John.
Thursday, March 5, 2026
Thursday 5th March 2026
John Cooper, Nigel Graham, Pete Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. The intention today was to expose the rock on the floor to see if it was suitable for capping. Kate went to the bottom to start and then Jude went down to help. After 15 loads of spoil it was time for Adrian to go and take a look. The decision was the rock was too big so was to be banged. Jude and Kate then came out and John went in with his drill. Two lines of 3 holes drilled to 500mm depth, 2 popped out the underside at about 450mm depth. A small hole was also drilled in a rock deemed too large for the bucket. Wayne brought across suitable cord which Adrian used in the holes. All the tools were moved to safe places and as John came out he detached the bottom double ladder and it was hauled out of shrapnel range (we hope). The draught blew the fumes out quickly. 2½ hours. John.
Saturday, February 28, 2026
Saturday 28th February 2026
John Cooper, Nigel Graham, Pete Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. Mud retaining wall at the North end continued today. Pete and Kate at the bottom. Pete wall building and Kate assisting and also digging out the floor. Four mixes of cement used. Had to lower another section of ladder for Pete to stand on so he could reach the top of his new wall. Also lowered several loads of building rock as there was none left at the bottom. Fourteen loads of spoil hauled out today and in addition Pete used several more filling up behind his wall. One frog rehomed today. At the end of the session the depth was measued at 15.2m. 2½ hours. John.
All photos taken near floor level. Descriptions are: facing then side.
![]() |
| South, West. Photo KL |
![]() |
| South, West. Photo KL |
![]() |
| South, East. Photo KL. |
![]() |
| North, East. Photo KL. |
![]() |
| North, East. Photo KL. |
![]() |
| North, West. Photo KL. |





