Thursday, November 26, 2026

Thursday 26th November 2026

John Cooper, Pete Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. Even cooler today at 3°C, overcast and damp. John drilled and fixed two pieces of 16mm threaded bar through the bottom builder’s ladder into the East and West walls. The angle bracket was not attached as the team thought it might be needed higher up. Then 2 good mixes of cement, split into 4 loads, used to finish off the North wall. As usual, buckets of larger rocks were lowered for use in wall building and smaller ones for packing behind the wall as and when requested. The piece of board from the old dig was removed. 2 hours. John.

Looking over wall into old dig. Photo KL.

Saturday, November 21, 2026

Saturday 21st November 2026

John Cooper, Pete Hann, and Kate Lawrence. Made a start on fixing the bottom section of builders ladder. Anchor on top left fixed. Need threaded bar for the two middle fixings and an angle bracket for the right foot. 1 hour. John.

Friday, November 20, 2026

Friday 20th November 2026

John Cooper, Pete Hann, Sarah Hann, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. Cool again today at 6°C, overcast with light rain to start. Pete and Sarah were just visiting having been on the SWT fungi walk. John hung a lifeline down the North end so he could attach himself at the various heights needed. A total of 4 full mixes of cement were sent down, split into 7 loads. Buckets of larger rocks were lowered for use in wall building and smaller ones for packing behind the wall as and when requested. The top of the wall is now about 50cm below the floor level of the top chamber. 2 hours. John.

Saturday, November 14, 2026

Saturday 14th November 2026

John Cooper, Nigel Graham, Pete Hann, Mike Kushy, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. Cool again today at 6°C, overcast with occasional sunny gaps in the clouds. John descended and hung the floodlight on the bottom, still to installed, ladder before returning to the surface. He noticed the ladder rungs were clean-washed from rain earlier in the week. Kate then descended to the bottom of the slot, Jude to the top of the slot and Adrian was stationed at John’s new wall so that gravel could be deposited behind it. Hauling started and 10 loads of gravel were stashed behind the wall before Adrian decided that was sufficient. He then descended to join Kate and more gravel and rocks hauled up. When Jude had had enough she came to the surface and Adrian station himself at the slot. More hauling until enough was declared and hauling for the day ceased. A total of 30 loads of gravel to the surface and 6 loads of rocks removed from the bottom. John then descended to collect his light but was persuaded to descend through the slot. Having done so he continued on down the hole in the West wall, along and down the passage heading West for a couple of metres before a cross rift was met. Left was blocked but right continued narrow for a couple of metres before pinching down to only 50mm wide. However through this could be seen another drop of a couple of metres and wider passage. Will need banging to pass and hope the roof further back doesn’t come down with the shock wave. The missing critter pot was found and can join the missing ball of string found earlier. I think that’s all the missing items finally retrieved. John out, Kate out and finally Adrian. 3½ hours. John.

Tuesday, November 10, 2026

Tuesday 10th November 2026

John Cooper, Mike Kushy, Kate Lawrence, Adrian Vanderplank and Jude Vanderplank. Cold today at 6°C with rain and wind making it seem even colder. John hung a lifeline rope down the North end where he was wall building. He attached himself in case his feet slipped off the small ledges he was using. A total of 4 full mixes of cement were sent down split into 8 loads. Buckets of larger rocks were lowered for use in wall building and smaller ones for packing behind the wall as and when requested. The wall has now reached the level where it reduces in width by 50% so should be quicker to build. There is room behind the wall for several loads of gravel to be dumped which will save it being lifted all the way to the surface and carried up the shakehole. 2 hours. John.